Restroom Remodel Update

As the single restroom upgrade by the Adoration Chapel nears completion, the next restroom to be upgraded is in the Cry Room. That 2nd upgrade is projected to be completed on or before April 18. The main Women’s restroom is scheduled to begin then after that.

During construction of the Woman’s main restroom, we plan to bring in a “Women Only” portable potty trailer with multiple stalls, sinks, running water (hot and cold), and to park it next to the Gift Shop kiosk for the four weeks the upgrade is anticipated to take. For women with physical handicaps, for access to restrooms during construction, please use either of the single restrooms inside the Cry Room and/or across from the Adoration Chapel.

After the main Women’s restroom upgrade is completed (around mid-May), the main Men’s restroom upgrade will begin. Multiple Porta Potties are scheduled to replace the Women’s Only Trailer for the men’s use while construction is underway. 

Please be aware of these plans and share them with whomever needs to know them.

Thank you,

Ramon Garcia, Facilities Director


The Restroom Remodel Project is underway. The construction will take place Mon-Fri during hours that will not interfere with scheduled Masses, rosaries and Divine Mercy chaplets. The plan is to make the church restrooms like those in the Parish Center, which will be a great improvement.

During this project, one restroom at a time will be remodeled, so that it creates the least impact on people attending our religious services. Please bear with us during this construction phase. Thank you for your patience and understanding while this church improvement project is being done.

The tentative plan and schedule for the remodeling of the restrooms is as follows:

Restroom #1 = located on the west side hallway in the back of the church

  • Status = underway
  • Duration = 3-4 weeks
  • Closed from 9:30–11:45 am, 1:00pm-2:45pm, 3:15-5:00pm
  • Open after hours

Restroom #2 = located within the Cry Room

  • Status = will commence when Restroom #1 is completed
  • Duration = 3-4 weeks
  • Closed from 9:30–11:45 am, 1:00pm-2:45pm, 3:15-5:00pm, 10:00pm-7:00am

Main Men’s Restroom #3 = located to the East of the Baptismal Font vestibule

  • Status = will commence when Restroom #2 is completed
  • Duration = 4-6 weeks
  • Closed during construction
  • Will provide a Men’s porta-potty solution during remodel
  • When completed, the Men’s Restroom will temporarily become the Women’s Restroom until the Women’s Restroom is completed

Main Women’s Restroom #4 = located to the East of the Baptismal Font vestibule

  • Status = will commence when Men’s Restroom is completed
  • Duration = 4-6 weeks
  • Closed during construction
  • Women will use the Men’s Restroom during construction
  • When completed, we will reassign the Women’s Restroom and Men’s Restrooms to the original genders

(More images can be found at www.stmaryp.org/photos/view/id/69579)